Refurbishment Update
14th December 2011Our newly refurbished church has now reopened but there is still work to be done. Read more about our refurbishment project.
Refurbishment news – 19th Dec 2010
19th December 2010The lift is now in position and is in the process of being fitted. The lift will provide access between the church and church hall for those unable to use the steps.
Refurbishment news – 21st Nov 2010
21st November 2010Apart from the lift, which will provide disabled access between the church and the hall and is on its way from Italy, most of the major construction work is complete. The portacabins will removed from the car park this week. … Continue reading
Refurbishment news – 14th Nov 2010
14th November 2010The porch inside the new entrance from the car park has been glazed. More paving stones have been laid on the outside of this entrance. The railings are now back in place having been stripped for repainting. The spiral staircase … Continue reading
Refurbishment news – 7th Nov 2010
7th November 2010All of the doors, both internal and external are now in place. The communion rail is back in place on the extended stage. Lights have been fitted both inside and outside. The steps up to the church from the hall … Continue reading
Refurbishment news – 24th Oct 2010
24th October 2010It is now a lot easier to see how the different parts of the refurbished building will fit together. The stairs are now on the spiral staircase. Work continues in the church itself. The porch for the new car park … Continue reading
Refurbishment news – 10th Oct 2010
10th October 2010Since the last update there has been considerable visible progress. All the major scaffolding has now gone, indicating that all stone cleaning, guttering and high level decoration is now finished. In the passage between the church and church hall, the … Continue reading
Refurbishment news – 22nd Aug 2010
22nd August 2010The scaffolding has come down from the hall, making the acoustic tiling, new lighting and paintwork visible. Some of the internal doors are fitted, others are under construction. The heating pipes will more or less remain intact. This pipe at … Continue reading
Refurbishment news – 8th Aug 2010
8th August 2010The kitchen units are being installed and storage units are going into the (former) lower classroom. The flat roof now has a protective covering. In the basement, much of the new wiring and pipework from the new boiler is in … Continue reading
Refurbishment news – 1st Aug 2010
1st August 2010The railings on the Castle Street side have been removed for stripping prior to repainting. Work has started on the lift, which will provide wheelchair access from the hall to the main church building.